Injection molding scheduling software for custom molders who plan presses in a spreadsheet
Injection molding scheduling software loads every job onto a specific press, counts the real shot time and every mold change, and tells you which orders will ship late while there is still time to act. ProductionPlanning.ai does that for custom and contract molders with 5 to 40 presses, in a browser, from 149 USD per plant a month with unlimited users. Orders, quotes and invoices stay in the ERP or QuickBooks setup you already run; the press schedule is what changes.
Free for 14 days on your own orders and machines. No card.
Machine shop, This week's schedule, finite capacity per work center
- On time
- Late
- Changeover
On time
0%
Bottleneck
0%
Shortages
0
Why a molding schedule breaks in a spreadsheet
A press schedule looks simple on a whiteboard: one row per press, one block per job. It breaks because the numbers behind each block are not simple.
- Run time depends on cycle time and cavity count, and a 4 cavity mold on a 30 second cycle runs a very different week from a single cavity mold on 45 seconds
- Every mold change costs one to three hours of setup, purge and first article, so the order in which jobs run decides how many hours the press actually molds
- Each mold fits only some presses, by tonnage, platen size and shot size, so a job cannot simply move to whatever press is free
- Material and color changes add purge time and scrap, and the planner groups jobs by resin and color to avoid them
- A customer pull ahead or a mold in the toolroom reshuffles the whole week, and nobody can say what the change pushes
The spreadsheet totals the hours and says the week fits. The sequence on each press says it does not, and that gap is where late shipments come from.
A worked example on two presses and four jobs
Here is a real shaped week for a molder running two 150 ton presses, P3 and P5, on two shifts, 06:00 to 22:00, Monday to Friday. At 85 percent efficiency each press gives 13.6 productive hours a day and 68 hours a week. Run time is shots times cycle time, and shots are parts divided by cavities.
| Job | Parts | Cavities | Cycle | Run hours | Mold change | Total | Due |
|---|---|---|---|---|---|---|---|
| J2 cap | 48,000 | 8 | 12 s | 20.0 | 1.5 h | 21.5 h | Tuesday |
| J1 housing | 20,000 | 4 | 30 s | 41.7 | 1.5 h | 43.2 h | Thursday |
| J4 clip, same color family as J2 | 24,000 | 8 | 12 s | 10.0 | 0.5 h | 10.5 h | Thursday |
| J3 bracket | 9,000 | 2 | 40 s | 50.0 | 1.5 h | 51.5 h | Friday |
In total the four jobs need 126.7 hours and the two presses offer 136, so a spreadsheet says the week works. The schedule says otherwise. J1 fits only P5, so it takes P5 until Thursday morning. J2, J4 and J3 run on P3 in due date order, with J4 straight after J2 to save the full mold change, and J3 finishes the following Tuesday, two working days late.
The scheduler shows that on Monday morning, not on Friday afternoon. You then test the options as plan versions. Moving J4 to P5 costs a full mold change and makes J4 a day late. A third shift on P3 for the week lifts it to 20.4 productive hours a day, and J3 finishes early on Friday, on time. That is the decision the plant manager actually needs to make, with the cost of each option in front of them.
How ProductionPlanning.ai models a molding floor
You do not need a molding specific data model to get a schedule you can run. Each element of the floor maps to something the scheduler already handles.
- Each press is a work center with its own shifts, holidays and planned maintenance
- Each part has a routing with minutes per part, which is cycle time divided by cavities, so a 30 second cycle on a 4 cavity mold is 0.125 minutes a part
- The presses a mold fits are listed as alternative work centers for that operation, so a job only moves where the mold can hang
- Mold changes are setup times per product family, and similar jobs (same resin, same color family) are grouped automatically on the Plant plan
- Secondary operations such as pad printing, assembly or packing are later steps in the same routing, scheduled with finite capacity too
- Efficiency per press covers the gap between book cycle time and what the press really runs
Setup is an afternoon: add the presses and shifts, import open orders and routings from a spreadsheet, and publish. The how it works page shows the four steps, and the machine scheduling software page shows the sequence per machine in more detail.
What the plant gets from a finite press schedule
- A projected finish date for every job next to its due date, with late jobs marked by the days they will miss
- The bottleneck press named, with its load for the week, so the third shift goes where it pays
- Plan versions on the Plant plan, so a pull ahead or a down mold is tested before anyone touches the floor
- A queue per press on a screen at the machine, where operators mark jobs started and finished (Plant plan)
- Material shortages per order, item and date, so a resin delivery that lands on Wednesday does not hide behind a Monday start
- One shared schedule for the planner, the shift leads, the toolroom and sales, without paying per seat
Sales gets dates it can quote, which is the point. Our article on how to calculate machine capacity works through the arithmetic behind the productive hours above.
Injection molding scheduling software compared honestly
Molders usually choose between three routes. Each one wins somewhere.
| Route | Scheduling depth | Mold and cavity data | Typical cost | Best for |
|---|---|---|---|---|
| Spreadsheet or whiteboard | Totals hours, no sequence, no finite capacity | Whatever the planner keeps | Planner time | One or two presses with stable repeat work |
| Plastics ERP and MES such as DelmiaWorks | Full scheduling inside the ERP, press monitoring, mold maintenance | Molds, cavities, family molds and tool life tracked as records | Per user on a quote, third party estimates from about 25,000 USD a year plus implementation | Multi plant suppliers with automotive or medical traceability and a team to own a rollout |
| Dedicated scheduler such as ProductionPlanning.ai | Finite capacity per press, setup by family, alternative presses, plan versions | Cavities folded into the time per part, mold fit as alternative presses | 149 USD per plant a month on Line, 429 USD on Plant, unlimited users | Custom molders whose orders and books already work and whose problem is late jobs |
Where a plastics ERP is the better buy: if you need mold life counters, cavity level scrap, live cycle monitoring from the press controller and lot traceability for an auditor, buy a system built for that. Our DelmiaWorks and IQMS alternative page compares the two in detail, and the DelmiaWorks pricing article works out the three year bill. If one mold can only hang on one press at a time and the same mold is shared by several jobs in a week, plan those jobs as one routing with grouping, since we do not track a mold as its own resource.
Which plan a molder needs
The Line plan covers up to 10 work centers and 500 open orders, which suits a molder with up to about eight presses and a couple of secondary stations. Most molders take Plant at 429 USD a month, because changeovers and grouping, plan versions, spreadsheet import and the press queues for operators are in Plant. Paying yearly halves both prices. All plans and limits are on the pricing page.
Molders who take over a mold book from another shop sometimes also inherit part designs a customer licensed from a patent holder; checking who holds those patents today is a short search on Assignee before the first production run. For background on the process itself, the injection moulding overview covers clamp tonnage, cycle phases and cavities.
Injection molding scheduling questions buyers ask
What is the best scheduling software for injection molding?
The best one fixes the problem you have. If you need mold life tracking, press monitoring and lot traceability, a plastics ERP and MES fits. If orders, quotes and invoices already work and jobs still ship late, a finite capacity scheduler that knows cycle time, cavities, mold changes and which presses each mold fits fixes the week in an afternoon.
How do you schedule injection molding machines?
Load each job onto a press the mold fits, with run time equal to parts divided by cavities times cycle time, plus the mold change. Sequence each press by due date, group jobs with the same resin and color to save purges, and check every finish date against its due date before you commit.
How much does injection molding scheduling software cost?
Plastics ERP systems price per user on a quote, with third party estimates from about 25,000 USD a year before implementation. ProductionPlanning.ai publishes its price: 149 USD per plant a month on Line and 429 USD on Plant, with unlimited users, no implementation fee, and half price when paid yearly.
Can the scheduler handle mold changeovers?
Yes. Setup time is set per product family, so a full mold change costs the hours it really takes while a run of parts in the same color family on a similar setup costs less. On the Plant plan, similar jobs are grouped automatically to cut the number of changes per press.
Does it work alongside our ERP?
Yes. Export open orders and routings from your ERP or a spreadsheet, import them, and publish a finite schedule the same day. Quoting, inventory and accounting stay where they are, and on the Plant plan the finished schedule exports back so promise dates match in both systems.
See your press schedule before the week starts
Run the demo with your own presses, cycle times and cavities, add a pull ahead, and see which job moves.
Your data stays yours. Export or delete it any time. No card to try the demo.